For the refurbishment of Bellevue Palace and the whole site, 860 million euros are budgeted, including risk and price reserves.[3][4] On top come 205 million euros for the temporary accommodation in Moabit, into which the federal president moved in the summer of 2026.[3][8] Together that is 1.065 billion euros. And for the fence around the site including video surveillance the taxpayers’ association names 23.9 million euros, on the arithmetic around 18,400 euros per metre.[6]

Important first: this is not an ordinary building-site fence, and the figures are not a closed final account. That is precisely why a close look is worth it.

What the billion covers

Costs of the Bellevue site and the temporary accommodation
Cost component€m
Refurbishment of Bellevue Palace146
Refurbishment of the administration building120
New main guardhouse and site-wide plant room173
External works and infrastructure (security installations, paths, geothermal energy, park, construction logistics)162
Construction and planning costs together601
Risk reserve188
Provision for construction price increases71
Refurbishment budget including reserves860
Temporary accommodation (project costs, separate budget of the federal property agency)205
Sum of both budgets1,065

Sources: Office of the Federal President[2][3] and the federal government’s answer[4]; temporary accommodation: Berliner Zeitung[8] and the federal government[4]. The last row is the addition of two separate budgets. According to the federal office for building and regional planning, furniture and interior fittings are budgeted separately and come on top.[6]

Three qualifications follow from this. First, the refurbishment of the palace itself costs 146 million euros according to the plan, not a billion; the billion arises from the whole site, the reserves and the temporary building. Second, the 259 million euros of reserves are planned risks and price increases, not money already spent; they correspond to around 43 per cent of the construction and planning costs. Third, the temporary accommodation is not a throwaway stopgap: after the federal president returns it is to serve other federal authorities permanently. Until then the Office of the Federal President pays rent, provisionally 16.8 million euros a year, and 9.2 million from the sixth year.[4][5]

How the costs have grown

How the figures named have developed
Point in timeState of play and costs named
2018 to 2020Search for an existing property as interim accommodation; none meets the requirements of security and representation, hence a new building.[2]
2020Planning begins, including a competition for the guard and control building.[1][4]
September 2021Temporary accommodation: €137m, later described as an upper limit.[7][8]
September 2023Temporary accommodation: €205m of project costs.[8]
25 February 2026The Office of the Federal President presents costs and a timetable for the whole site: €601m plus €259m of reserves.[3][9]
August 2026The federal office for building and regional planning takes over the site; the preparatory works begin four months later than planned. Budget: €860m.[4]
1 October 2026The black book of the taxpayers’ association criticises the fence: €23.9m for 1,300 metres.[6]

The robust statement about the increase in costs is therefore this: between 2021 and 2023 the temporary accommodation rose from 137 to 205 million euros, by almost 50 per cent.[7][8] The statement that “the refurbishment of the palace rose from 137 million to over a billion”, by contrast, would be wrong, because it mixes two projects and different scopes of cost. We found no published earlier overall estimate for the refurbishment of the site against which today’s 860 million could honestly be compared.

The fence in detail

Fence including video surveillance, per linear metre

around €18,400

23.9 million euros divided by 1,300 metres gives 18,384.62 euros per metre. Ten metres work out at around 184,000 euros, a hundred metres at around 1.84 million.[6]

A proportional conversion of the whole package, not a unit price for a metre of steel fence.

What is actually being renewed is confirmed by the Office of the Federal President: the permanent fence along the whole 1,300-metre outer boundary of the site of around ten hectares, and the video surveillance along that boundary. The analogue video technology, around 30 years old, is being digitised.[1][2] The federal government assigns fence, video surveillance and bollards to external works, which come to 162 million euros in total.[4]

No official publication shows a separate price of 23.9 million euros. The figure comes from the black book.[6] In response to the criticism the Office of the Federal President merely referred to its website.[10] A pure price for materials or installation cannot be derived from it, and a breakdown between fence, cameras and further works is not public.

Where the criticism bites

The temporary accommodation alone became 68 million euros more expensive. These additional costs on their own come to almost three times the fence package.[6][8] Whether a new building was needed at all was doubted early on: in 2021 Berliner Zeitung pointed to 121,000 square metres of empty federally owned office space.[13]

The guardhouse and plant room together cost 173 million euros, more than the refurbishment of the historic palace at 146 million.[2][3] The project thus goes far beyond refurbishing a palace.

The risk and price buffer of 259 million euros is larger than the entire budget of the temporary new building.[3][8] Such a buffer is not automatically uneconomic, but it is an order of magnitude that calls for public scrutiny.

The price of around 18,400 euros per metre is a vivid point of criticism. Without a specification of the works and a robust comparison, though, it does not on its own prove that the contract is overpriced.

What belongs to a fair assessment

The Office of the Federal President names concrete reasons for the refurbishment: a roof leaking in places, corrosion in the floor slabs, outdated building services, considerable fire safety defects above all in the administration building, and windows that do not meet security requirements. A conference area in the palace and an additional office floor in the administration building were dropped.[1][2][4]

The comparison with the refurbishment of 2004 and 2005 carries only so far: back then it was mainly the north wing that was partly refurbished, in 20 months, and Charlottenburg Palace served only for individual events, not as a substitute official residence.[4][11] In the summer of 2026 federal president Steinmeier said the palace was not the cost driver; a ZDF fact check assessed that as partly accurate.[12]

The need for refurbishment is thus established. Whether all the measures and prices are economically appropriate is another question.

What the federal government has to disclose

For a robust assessment of the fence, the federal office for building and regional planning or the Office of the Federal President would have to answer at least six questions. How much falls to the fence, how much to the video surveillance? Are demolition, foundations, earthworks, cable routes, power supply and the restoration of the ground included? What particular protection requirements does the installation have to meet? Are planning costs and reserves contained in the 23.9 million? Is this an estimate, a contract awarded or works that have been invoiced? And which cheaper variants were examined and why were they rejected?

These are questions for examination, not claims about what is in this budget. The documents published so far do not answer them for the fence.

A need for refurbishment is no blank cheque for any invoice. If Bellevue together with the temporary new building becomes a billion-euro project, and the fence with cameras alone is to cost 18,400 euros per metre on the arithmetic, then the federal government has to explain publicly which works justify these sums and which cheaper alternatives were examined. Pointing to higher security requirements does not on its own replace a comprehensible calculation.

Andreas W. HerbCEO MBG Group, Paderborn

CHECK


What was checked before publication

  • Every step of the arithmetic has been recalculated and follows from the starting values named.
  • The figures were checked on 7 October 2026 against the account given by the Office of the Federal President, the federal government’s answer of 24 September 2026 and the other sources.
  • The 23.9 million euros for the fence and video surveillance appear in the black book of the taxpayers’ association (source 6), not in any official publication. Whether reserves or further works are included is not public.
  • The 1,065 million euros are the sum of two separate budgets: according to the federal government the temporary accommodation is not part of the refurbishment but a building of the federal property agency, for which the Office of the Federal President pays rent (source 4).

SOURCES


Sources

Every number in the text leads to its source. The origin is given at each entry: official, media report, trade association, institute or data portal. Titles stay in the original language, so that each document can still be found.

  1. [1] Bundespräsidialamt

    Baumaßnahmen an Schloss Bellevue

    Official source↑ back to the text

  2. [2] Bundespräsidialamt

    Grundlegende Sanierung des Amtssitzes des Bundespräsidenten (Kurzüberblick)

    Official source↑ back to the text

  3. [3] Bundespräsidialamt, 25.02.2026

    Schloss Bellevue und Bundespräsidialamt werden grundlegend saniert – Umzug im Sommer 2026

    Official source↑ back to the text

  4. [4] Deutscher Bundestag, 24.09.2026

    Drucksache 21/8214: Antwort der Bundesregierung auf eine Kleine Anfrage zur Sanierung des Amtssitzes des Bundespräsidenten

    Official source↑ back to the text

  5. [5] Bundesamt für Bauwesen und Raumordnung

    Häufig gestellte Fragen zum Bürogebäude für Bundesbehörden

    Official source↑ back to the text

  6. [6] Bund der Steuerzahler, Schwarzbuch 2026/27, 01.10.2026

    Ein Präsidentenzaun für 24 Mio. Euro

    Trade association↑ back to the text

  7. [7] Berliner Zeitung, 02.09.2021

    Bau der Zwischenunterkunft für den Bundespräsidenten kostet 137 Millionen Euro

    Media report↑ back to the text

  8. [8] Berliner Zeitung, 14.09.2023

    Geplantes Ausweichquartier für den Bundespräsidenten wird teurer

    Media report↑ back to the text

  9. [9] Tagesspiegel (dpa), 25.02.2026

    Schloss Bellevue wird teurer: Sanierung von Steinmeiers Amtssitz soll 601 Millionen kosten

    Media report↑ back to the text

  10. [10] Volksstimme (dpa), 01.10.2026

    Steuerzahlerbund rügt teuren Airport und Bellevue-Sanierung

    Media report↑ back to the text

  11. [11] Bundespräsidialamt, Stand 01.06.2026

    Häufig gestellte Fragen zu den Baumaßnahmen am Berliner Amtssitz

    Official source↑ back to the text

  12. [12] ZDFheute, 12.07.2026

    Faktencheck zum Sommerinterview mit Frank-Walter Steinmeier

    Media report↑ back to the text

  13. [13] Berliner Zeitung, 21.09.2021

    137 Millionen Euro: Braucht der Bundespräsident wirklich ein Ausweichquartier?

    Media report↑ back to the text

CORRECTIONS


Corrections

No corrections since publication on 07/10/2026. Every substantive change appears here with its date, reason and previous wording.

This page is opinion. Our fact checks are not.